Star Vertex Infrastructures | Steel Structure Experts Since 2019
Facebook Instagram LinkedIn

✅ Completed Projects

Sr. No. Project Name Location Total MT Execution Type Completion Year
1AIIMSBilaspur, Himachal Pradesh2880 MTErection2019
2M3M IFCGurugram365 MTFabrication2019
3CyberthumNoida321 MTFabrication2020
4Omaxe Chandni ChowkDelhi950 MTFabrication2020
5Industrial Gum PlantAkbarpur Barota, Haryana680 MTErection2020
6Ravindra Bhavan (Auditorium)Canacona, Goa240 MTFabrication & Erection2021
7Pillet PlantAngul, Odisha250 MTFabrication2022
8WHO OfficeDelhi150 MTFabrication2022
9Cyberthum (Bhutani Group)Noida127 MTFabrication2023
10Rail Forging PlantRaigarh121 MTFabrication2023
11Hydrangea ProjectShimla88 MTFabrication2023
12SAF ProjectRaigarh139 MTFabrication2023
13Barmer ProjectJharsuguda450 MTFabrication2023
14Patna AirportPatna, Bihar700 MTErection2024

* Ravindra Bhavan Project was completed in record time of 65 working days.

🔄 Ongoing Projects

Sr. No. Project Name Location Total MT Execution Type
1Chappra FlyoverMuzaffarpur, Bihar700 MTFabrication
2Betkuchi ProjectKamrup, Guwahati1000 MTFabrication
3Coke Oven UnitAngul, Odisha360 MTFabrication
4SMS Caster UnitAngul, Odisha300 MTFabrication
5Netaji Subhash PlaceDelhi280 MTFabrication